Project: Saray settlement Secondary school No. 2 named after A. Muzaffarov
Our role in the project: General Contractor
Performed works: demolition, excavation, reinforced concrete and metal construction, facade, internal finishing, external communication lines (mechanical, electrical and plumbing), landscape design – amenity renovation.
Project duration: November 2020 – March 2022
Construction area: 6220 m2
Total area: 14210 m2
Height: 18.6 m
Number of floors: 4